System dynamic based project duration simulation of construction projects

Document Type : Original Article

Authors
Department of Construction Engineering and Management, Faculty of Civil Engineering, KN Toosi University of Technology, Tehran, Iran.
Abstract
In this study, after identifying the factors and parameters affecting the duration of construction projects, the system thinking approach and system dynamics method are used to find the root causes, relationships and feedback between the factors. Library studies were used to identify the factors affecting the duration of the projects and Delphi interviews with 22 experts were used to improve and supplement these factors. Then, a conceptual model based on causal loops is presented to better understanding of the relationships between variables. Afterwards, using the approach governing the system dynamics method, a flow diagram is compiled to better understand and learn and also to more dynamic analysis of the research problem. The accuracy of the accumulation flow model has been measured with some tests, including reviewing and evaluating the behavior and structure of the model, and also four main scenarios were formulated for implementing different executive policies. Based on the results, the behavior and performance of the model have been evaluated and analyzed. The results obtained from the evaluations confirm the correct performance of the proposed model. Simulation results across four scenarios demonstrated that the most effective levers for project acceleration are the minimization of owner-driven scope/method changes and the strategic investment in human resource development (training and fair compensation), which significantly mitigate project delays by improving system efficiency. It is hoped that the understanding gained from this learning system will provide the necessary basis for making better and more efficient decisions in the field of project time.
Keywords

  1. Kerzner, Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Hoboken, NJ, USA: John Wiley & Sons, 2017. [Online].
  2. Williams, “Assessing extension of time delays on major projects,” International Journal of Project Management, vol. 21, no. 1, pp. 19–26, 2003. [Online]. Available: https://doi.org/10.1016/S0263-7863(01)00060-6
  3. Sambasivan and Y. W. Soon, “Causes and effects of delays in Malaysian construction industry,” International Journal of Project Management, vol. 25, no. 5, pp. 517–526, 2007. [Online]. Available: https://doi.org/10.1016/j.ijproman.2006.11.007
  4. Ndekugri, N. Braimah, and R. Gameson, “Delay analysis within construction contracting organizations,” Journal of Construction Engineering and Management, vol. 134, no. 9, pp. 692–700, 2008. [Online]. Available: https://doi.org/10.1061/(ASCE)0733-9364(2008)134:9(692)
  5. Sweis, R. Sweis, A. A. Hammad, and A. Shboul, “Delays in construction projects: The case of Jordan,” International Journal of Project Management, vol. 26, no. 6, pp. 665–674, 2008. [Online]. Available: https://doi.org/10.1016/j.ijproman.2007.09.009
  6. Pourrostam and A. Ismail, “Causes and effects of delay in Iranian construction projects,” International Journal of Engineering and Technology, vol. 4, no. 5, pp. 1793–8236, 2012. [Online].
  7. Abbasnejad and H. Izadi Moud, “Construction delays in Iranian civil engineering projects: An approach to the financial security of construction business,” Life Science Journal, vol. 10, no. 2, pp. 2632–2637, 2013. [Online].
  8. Mukuka, C. Aigbavboa, and W. Thwala, “A theoretical assessment of the causes and effects of construction project delay,” in Proceeding CEE 2013, pp. 174–177, 2013. [Online]. Available: https://ceeconference.org
  9. D. Owolabi, M. A. Lekan, C. O. Oloke, O. Olusanya, P. Tunji-Olayeni, and P. D. Owolabi, “Causes and effect of delay on project construction delivery time,” International Journal of Education and Research, vol. 2, no. 2, pp. 197–208, 2014. [Online].
  10. Tafazzoli and P. P. Shrestha, “Investigating causes of delay in US construction projects,” in Proc. 53rd ASC Annu. Int. Conf., pp. 611–621, 2017. [Online].
  11. M. Lyneis, K. G. Cooper, and S. A. Els, “Strategic management of complex projects: A case study using system dynamics,” System Dynamics Review, vol. 17, no. 3, pp. 237–260, 2001. [Online].
  12. N. Repenning, “A simulation-based approach to understanding the dynamics of innovation implementation,” Sloan School of Management, MIT, Cambridge, MA, USA, Tech. Rep., 1999. [Online].
  13. Howick, Using System Dynamics Models with Litigation Audiences. Dept. of Management Science, Univ. of Strathclyde, Glasgow, U.K., 2001. [Online]. Available: https://doi.org/10.1016/j.ejor.2003.08.041
  14. Chritamara, S. O. Ogunlana, and N. Bach, “System dynamics modeling of design and build construction projects,” Construction Innovation, vol. 4, no. 3, pp. 593-603, 2012. [Online]. Available: https://doi.org/10.5592/otmcj.2012.3.3
  15. E. Love, “Using systems dynamics to better understand change and rework in construction project management systems,” International Journal of Project Management, vol. 20, no. 6, pp. 425–436, 2002. [Online]. Available: https://doi.org/10.1016/S0263-7863(01)00039-4
  16. M. Bonner, R. W. Ruekert, and O. C. Walker, Jr., “Upper management control of new product development projects and project performance,” Journal of Product Innovation Management, vol. 19, no. 3, pp. 233–245, 2002. [Online].
  17. Howick, “Using system dynamics to analyse disruption and delay in complex projects for litigation: Can the modelling purposes be met?,” Journal of the Operational Research Society, vol. 54, no. 3, pp. 222–229, 2003. [Online]. Available: https://doi.org/10.1057/palgrave.jors.2601502
  18. K. Chang, “Quantifying the impact of schedule compression on labor productivity for mechanical and sheet metal contractor,” Journal of Construction Engineering and Management, vol. 133, no. 4, pp. 287–296, 2007. [Online].
  19. H. Sebt, A. Gereei, and T. H. Naghash, “A comprehensive framework for integrated management of opportunities and threats by using dynamic system,” International Journal of Civil Engineering, vol. 7, no. 3, pp. 161–169, 2009. [Online].
  20. Dangerfield, S. Green, and S. Austin, “Understanding construction competitiveness: The contribution of system dynamics,” Construction Innovation, vol. 10, no. 4, pp. 408-420, 2010. [Online]. Available: https://doi.org/10.1108/14714171011083579
  21. J. Mawdesley and S. Al-Jibouri, “Modelling construction project productivity using systems dynamics approach,” International Journal of Productivity and Performance Management, vol. 59, no. 1, pp. 18-36, 2010. [Online]. Available: https://doi.org/10.1108/17410401011006095
  22. K. Wan, M. Kumaraswamy, and D. T. Liu, “Dynamic modelling of building services projects: A simulation model for real-life projects in the Hong Kong construction industry,” Mathematical and Computer Modelling, vol. 57, nos. 9–10, pp. 2054–2066, 2013. [Online]. Available: https://doi.org/10.6106/JCEPM.2013.3.3.035
  23. Alvanchi, S. Lee, and S. AbouRizk, “Dynamics of working hours in construction,” Journal of Construction Engineering and Management, vol. 138, no. 1, pp. 66–77, 2012. [Online]. Available: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000384
  24. Ye, “Simulating effects of management measures on the improvement of the environmental performance of construction waste management,” Resources, Conservation and Recycling, vol. 62, pp. 56–63, 2012. [Online]. Available: https://doi.org/10.1016/j.resconrec.2012.01.010
  25. Yu-jing, “Application of system dynamics in construction project planning and control,” in Proc. 2012 2nd Int. Conf. on Business Computing and Global Informatization (BCGI). IEEE, 2012. [Online]. Available: https://doi.org/10.1109/BCGIN.2012.20
  26. Han, P. Love, and F. Peña-Mora, “A system dynamics model for assessing the impacts of design errors in construction projects,” Mathematical and Computer Modelling, vol. 57, nos. 9–10, pp. 2044–2053, 2013. [Online]. Available: https://doi.org/10.1016/j.mcm.2011.06.039
  27. Nasirzadeh and P. Nojedehi, “Dynamic modeling of labor productivity in construction projects,” International Journal of Project Management, vol. 31, no. 6, pp. 903–911, 2013. [Online]. Available: https://doi.org/10.1016/j.ijproman.2012.11.003
  28. P. Warhoe, Applying Earned Value Management to Design-Bid-Build Projects to Assess Productivity Disruption: A System Dynamics Approach. Boca Raton, FL, USA: Universal-Publishers, 2013. [Online]. Available: https://www.universal-publishers.com
  29. Nasirzadeh, “Modeling quality management in construction projects,” International Journal of Civil Engineering, vol. 11, no. 1, pp. 14–22, 2013. [Online]. Available: https://ijce.iust.ac.ir
  30. Ding, “A system dynamics-based environmental performance simulation of construction waste reduction management in China,” Waste Management, vol. 51, pp. 130–141, 2016. [Online]. Available: https://doi.org/10.1016/j.wasman.2016.03.001
  31. Abotaleb and I. H. El-adaway, “Managing construction projects through dynamic modeling: Reviewing the existing body of knowledge and deriving future research directions,” Journal of Management in Engineering, vol. 34, no. 6, p. 04018033, 2018. [Online]. Available: https://doi.org/10.1061/(ASCE)CO.1943-7862.0001797
  32. G. Al-Kofahi, A. Mahdavian, and A. Oloufa, “System dynamics modeling approach to quantify change orders impact on labor productivity: Principles and model development comparative study,” International Journal of Construction Management, pp. 1–12, 2020. [Online]. Available: https://doi.org/10.1080/15623599.2020.1711494
  33. Mohammadrezaytayebi, M. H. Sebt, and M. R. Afshar, “Introducing a system dynamic–based model of quality estimation for construction industry subcontractors’ works,” International Journal of Construction Management, pp. 1–15, 2021. [Online]. Available: https://doi.org/10.1080/15623599.2021.1899592
  34. Golshanimanes, “Providing a system dynamic model to predict construction status in Iran using sustainable development indicators,” Journal of Industrial Engineering International, vol. 17, no. 3, pp. 1–19, 2021. [Online]. Available: https://doi.org/10.30495/JIEI.2021.1929444.1119
  35. Wang, “System dynamics tool for entropy-based risk control on sleeve grouting in prefabricated buildings,” Engineering, Construction and Architectural Management, vol. 29, no. ?, pp. ?, 2022. [Online]. Available: https://doi.org/10.1108/ECAM-01-2021-0048
  36. Dadashi Haji and B. Behnam, “An automated BIM and system dynamics tool for assessing safety leading indicators in construction projects,” International Journal of Building Pathology and Adaptation, vol. 43, no. 3, pp. 414-439, 2023. [Online]. Available: https://doi.org/10.1108/IJBPA-05-2022-0072
  37. Riaz, K. I. A. Khan, F. Ullah, M. B. Tahir, M. Alqurashi, and B. T. Alsulami, “Key factors for implementation of total quality management in construction sector: A system dynamics approach,” Ain Shams Engineering Journal, vol. 14, no. ?, pp. ?, 2023. [Online]. Available: https://doi.org/10.1016/j.asej.2022.101903
  38. A. Al-Arihshi, S. Alwabel, B. Almansour, and M. Alshahrani, “BIM impact on construction project time using system dynamics in Saudi Arabia’s construction,” Buildings, vol. 13, no. 9, p. 2267, 2023. [Online]. Available: https://doi.org/10.3390/buildings13092267
  39. Zhao, X. Qin, and C. Chen, “Research on risk factors of construction project delays based on system dynamics,” Procedia Computer Science, in Proc. 12th Int. Conf. on Information Technology and Quantitative Management (ITQM 2025), vol. 266, pp. 349–356, 2025. [Online]. https://doi.org/10.1016/j.procs.2025.08.044
  40. Bryman, Social Research Methods. Oxford, U.K.: Oxford Univ. Press, 2016. [Online].
  41. Brockhoff, “The performance of forecasting groups in computer dialogue and face-to-face discussion,” in Large-Scale Projects: Management Trends for Major Projects. Addison-Wesley Publishing Co., 1975. [Online].
  42. M. Boje and J. K. Murnighan, “Group confidence pressures in iterative decisions,” Management Science, vol. 28, no. 10, pp. 1187–1196, 1982. [Online]. Available: https://doi.org/10.1287/mnsc.28.10.1187
  43. R. Hallowell and J. A. Gambatese, “Qualitative research: Application of the Delphi method to CEM research,” Journal of Construction Engineering and Management, vol. 136, no. 1, pp. 99–107, 2010. [Online]. Available: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000137
  44. Sushil, System Dynamics: A Practical Approach for Managerial Problems. New Delhi, India: Wiley Eastern Ltd., 1993. [Online].
  45. Park, “Model-based dynamic resource management for construction projects,” Automation in Construction, vol. 14, no. 5, pp. 585–598, 2005. [Online]. Available: https://doi.org/10.3390/app11083681
  46. D. Sterman, “System dynamics modeling for project management,” unpublished manuscript, Cambridge, MA, USA, 1992. [Online].
  47. N. Ford, “The dynamics of project management: An investigation of the impacts of project processes and coordination on performance,” Ph.D. dissertation, Massachusetts Institute of Technology, Boston, MA, USA, 1995. [Online]. Available: https://dspace.mit.edu
  48. A. Assaf and S. Al-Hejji, “Causes of delay in large construction projects,” International Journal of Project Management, vol. 24, no. 4, pp. 349–357, 2006. [Online]. Available: https://doi.org/10.1016/j.ijproman.2005.11.010
  49. Kermanshachi, R. Thakur, and P. Govan, “Discovering the impact of late change orders and rework on labor productivity: A water treatment case study analysis using system dynamics modeling,” in Proc. Construction Research Congress 2018, 2018. [Online]. Available: https://doi.org/10.1061/9780784481295.069
  50. P. Davidson and G. Huot, “Large-scale projects: Management trends for major projects,” Cost Engineering, vol. 33, no. 2, p. 15, 1991. [Online].
  51. M. Lyneis and D. N. Ford, “System dynamics applied to project management: A survey, assessment, and directions for future research,” System Dynamics Review, vol. 23, nos. 2–3, pp. 157–189, 2007. [Online]. Available: https://onlinelibrary.wiley.com
  52. Loosemore, Essentials of Construction Project Management. Sydney, Australia: UNSW Press, 2003. [Online]. Available: https://www.unswpress.org.au
  53. Odeh and H. T. Battaineh, “Causes of construction delay: Traditional contracts,” International Journal of Project Management, vol. 20, no. 1, pp. 67–73, 2002. [Online]. Available: https://doi.org/10.1016/S0263-7863(00)00037-5
  54. Sayedyahosseini, “Application of system dynamics model in management of hydroelectric power plants,” Iranian Association for Energy Economics (IRAEE), Tehran, Iran, Tech. Rep., 2009. [Online]. Available: https://iraee.org/en/home-en/
  55. W. Forrester, Urban Dynamics. Cambridge, MA, USA: MIT Press, 1969.
  56. D. Sterman, Business Dynamics: Systems Thinking and Modeling for a Complex World. New York, NY, USA: McGraw-Hill, 2000.
  57.  
Send comment about this article
Enter Name.
Enter a valid email address.
Enter a vaid affiliation.
Enter comments (At leaset 10 words)
CAPTCHA Image
Enter Security Code Correctly.